Tuesday, May 27, 2008

Exit Eddie Hurt

We fired our architect Eddie Hurt today. He's mislead us for far too long now. We're tired of his half-truths and obfuscations. It turns out our project was nowhere near where Eddie led us to believe it was. Also, he never filed it with the city.

We've found someone, Steve Krebs (http://www.krebsdesigngroup.com), to take Eddie's work and bring it to completion.

Wednesday, May 14, 2008

The logjam has broken!

It took four excruciating months, but Eddie has finally finished the plans and submitted to the city. So, we are back to interviewing contractors. Also, we signed a short lease on an apartment in town and will start moving over the next few weeks. If all goes well, our project will finish this year!

Tuesday, March 18, 2008

Hurry up and wait

Our architect, Eddie, is having trouble getting the engineer he hired to finish our job. So, now, Eddie has hired a new engineer. Hopefully, we can have construction drawings this week.

>|

Wednesday, February 13, 2008

Thursday, January 31, 2008

The Design

Here are the main design docs for our Remodel (click for larger images):

Main Floor
Master Bedroom/Bathroom

Wednesday, January 30, 2008

A major milestone!

We purchased our cabinets today. We're still recovering from the sticker shock. In the meantime, enjoy this design drawing:

Wednesday, January 23, 2008

Premature contractor interviews

The plans Eddie gave us are not enough to use to interview contractors. I learn more about this process every day. Time to light a fire under Eddie >:|